Project Server 2010 Error Id 24006

Detalhes: id='24006' name='ReportingProjectChangeMessageFailed' uid='58161929-3ec3-4f38-b57c-7837e9ea0c27' QueueMessageBody='Project UID='99a96cab-1398-4c06-ad71-2805c55df1ac'. The ULS log entry associated with the initial Queue errors above (for the benefit of the search engines): 05/01/2012 11:57:55.67 Microsoft.Office.Project.Server (0x1D74) 0x335C Project Server Reporting atwj Critical Standard Information:PSI Entry Best regards, Brian. Its current state is FailedNotBlocking. More about the author

If you need any assistance with these steps then feel free to open a support incident – and when I say free I mean free – this is a bug and The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmTask". Sub Job ID is: . The statement has been terminated.'. More about the author

The conflict occurred in database "DB_Reporting", table "dbo.MSP_EpmTask". Best regards, Brian. This is an error in the current version of Project Server 2013 (SP1, CU1). august 2014 ProjectCheckinNotifyWorkflowMessage - Project Server While developing a new program in Project Server CSOM today I got a strange error message in the queue: GeneralQueueJobFailed(26000) -WorkflowCheckinNotify.ProjectCheckinNotifyWorkflowMessage.

  • PublishType='ProjectPublish" Error='The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID".
  • Standard Information:PSI Entry Point: Project User: Correlation Id: b0df3541-e9e2-442a-ae62-553d07d9139f PWA Site URL: http://…/pwa SSP Name: SharedServices PSError: ReportingProjectChangeMessageFailed (24006) RDS: The request to synchronize change(s) to project Project UID='fa51b8e3-9b78-4cf3-9890-75cf2af4d91f'.
  • The statement has been terminated.'.
  • Yo can recreate the Reporting Database. 1.
  • The statement has been terminated.'.
  • I can do the clean up however I'd like to get a permanent fix.
  • We now understand the root cause and have a fix coming hopefully in the June 2012 Cumulative Update for Project Professional 2010 (no promises – but that is the current target)
  • ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID".

If you need help then open a support incident with us – we do not charge for bug related incidents – so we can help you through this. The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmTask". database maintenance plan necessary Project server Queue Job Services Optimization Project Server Problems with April 2015 SharePoint Updates Delegated user not able to see Manager Timesheet project server 2013 sp1 Daily The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmTask".

The conflict occurred in database "P13_CLIENT_ProjectServer", table "dbo.MSP_EpmAssignment". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmTask". The conflict occurred in the MSP_EPMAssignmentBaseline Table. https://guidesharepoint.wordpress.com/tag/project-server-2010-error-24006-26000/ The conflict occurred in database "DB_Reporting", table "dbo.MSP_EpmTask".

TaskBaselinesTimephasedDataSync.GetTimephasedDataForEntities(IEnumerable`1 entities, Int32 interval, Int32& index) So something is wrong in the baseline, unfortunately turns out to be nothing small! ok, i will try to open case, and after that e-mail to you. Follow the restore in the queue. First the best way to avoid this issue, and then on to the detection and clean up at the database level.

The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmTask". http://technicaltrix.blogspot.com/2014_08_01_archive.html Message: 'ReportingProjectChangeMessageFailed' Error:Object reference not set to an instance of an object. In short, the issue is ghost or orphan baseline records. GeneralQueueJobFailed (26000) - ReportingProjectPublish.ReportProjectPublishMessageEx These failures are for the reporting job – so will mean that reports based on the reporting database, and any fresh OLAP cube builds could be missing

Detalhes: id='26000′ name='GeneralQueueJobFailed' uid='17d35b4d-b58a-40fc-96a4-9a0f1774f3cf' JobUID='50ad5fc3-a1d2-41d4-ac98-98bb11e445a8′ ComputerName='EPMGERBA04′ GroupType='ReportingProjectPublish' MessageType='ReportProjectPublishMessageEx' MessageId='1′ Stage=". my review here The statement has been terminated.'. The statement has been terminated.'. As the bad stuff will also get persisted to the local cache, this is one of those rare occasions when you will find me suggesting that the project is removed from

| Search MSDN Search all blogs Search this blog Sign in Brian Smith's Microsoft Planner and Project Support Blog Brian Smith's Microsoft Planner and Project Support Blog All the latest information The statement has been terminated.. o ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID". click site Error message from queue: • Reporting message processor failed: o ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID".

See below. The statement has been terminated.'. Fill in your details below or click an icon to log in: Email (required) (Address never made public) Name (required) Website You are commenting using your WordPress.com account. (LogOut/Change) You are

Detaljer: id='24006' name='ReportingProjectChangeMessageFailed' uid='b12c9639-f86c-47e3-af28-9b016b5f576a' QueueMessageBody='Project UID='f12dced7-1d84-47e0-86ee-4049dbd9b1cd'.

Inserting the task manually through the PWA also causes the error. Please only offer solutions where you are confident that your answer is the correct one. PublishType='ProjectPublish'" Error="Exception of type 'System.OutOfMemoryException' was thrown." /> navigate to this website The conflict occurred in database "DB_Reporting", table "dbo.MSP_EpmTask".

Hope this help you. Cole says: August 4, 2014 at 7:38 am We applied MSP 2010 SP2 in August 2013, and have had several occurrences of "orphaned baselines" since. Backup all the custom fields. Sorry I could not be of more help.Dale A.